WRA borehole permit in Kenya: steps and cost

The Water Resources Authority approves a borehole twice: before you drill, and again before you use the water. The steps, the official fees by category and the deadlines the Regulations set, in the order you meet them.

Updated 28 Nov 2026 · 8 min read By Peter Kamau
Road between farm fields in Mau Narok
On this pageThe two approvalsStep by stepOfficial fees by categoryCosts that are not WRA feesFiling the permit when you build from a distance
The short answer

You need WRA authorisation before drilling and a water use permit after the borehole is finished, valid for five years. The official application fee is KSh 2,000 for Category A and KSh 20,000 for Category B, with the permit itself costing KSh 1,000 or KSh 25,000 (Water Resources Regulations, 2021).

This guide is part of the Jua Pumps guides. It follows the permit through a build, so read it alongside the borehole drilling cost guide. Once the borehole is approved and tested, pick a pump in solar borehole pumps, size it with the sizing calculator, or see how borehole solarization works. The fees and deadlines below are those printed in the Water Resources Regulations, 2021, which sit under the Water Act, 2016. WRA can amend its fees, so confirm the current amount with WRA before you pay.

The two approvals

  1. Authorisation to drill. You apply before any work starts. WRA decides the category of your water use, then approves, refuses or sets conditions.
  2. Water use permit. After the borehole is built and inspected, you apply for the permit that lets you take water. It runs for five years.

Abstracting water under an authorisation when you should hold a permit is also an offence, WRA states on its permit page. The authorisation is for building. The permit is for using.

Step by step

  1. Hire a qualified professional for the survey. The hydrogeological survey report must follow the form in the Fourth Schedule of the Regulations, and the report is prepared by a qualified and licensed water sector professional. See what the survey costs.
  2. File the application with the fee. The form is WRA Form 001. The application goes in before you build. For Categories B, C and D, the Regulations also require a site assessment report or hydrogeological survey report and an environmental impact assessment study report. Applying is done through WRA, which names its eCitizen customer portal as the place to apply.
  3. WRA registers it and checks the site. The application gets a file number. Groundwater files carry a “/G” suffix. WRA publicises the application and verifies the site.
  4. Local comments. The water resource users’ association, or a local group if none exists, has 30 days to comment. WRA then has 14 days to decide. If nobody comments, WRA may decide after the 30 days. For Categories C and D you must also publish the application in a national newspaper and in the Kenya Gazette.
  5. Authorisation to construct. Categories C and D go through the basin committees, and Category D is decided at WRA headquarters. If you do not build within the time limit on the authorisation, you apply for an extension.
  6. Drill and test. Only a qualified contractor may drill, under supervision. A borehole with a motorised pump gets test pumping of at least 24 hours, plus at least 20 hours of recovery.
  7. Send the completion record. Within 28 days of completing the works, submit the borehole completion record (WRA Form 009) with the completion certificate. WRA must analyse this data before it issues a permit.
  8. Inspection. WRA inspects the works against the conditions. If it is not satisfied, it issues an order within 14 days listing what to fix.
  9. Apply for the permit. Within 30 days of completing the works, you apply for the water use permit. WRA must issue it within 31 days of a complete application, once the works pass inspection.
  10. Keep it alive. Permits are renewable every five years. A Category B, C or D holder must keep a daily record of the water taken, in cubic metres a day.

Official fees by category

These are the fees in the Second Schedule of the Water Resources Regulations, 2021, in KSh:

Water use category Assessing the application Issuing the first permit (5 years) Renewal or variation (includes the new permit)
Category A 2,000 1,000 1,000
Category B 20,000 25,000 45,000
Category C 40,000 50,000 90,000
Category D 80,000 100,000 180,000

Category A is for use that WRA considers low risk to the water resource because of its scale. WRA decides the category, and the criteria are WRA’s to set. Ask your hydrogeologist which category WRA is likely to give your plot.

The schedule adds that groundwater applications come with a payment for physical and chemical analysis of the water. A permit transfer or variation application is KSh 4,000 each. The same schedule sets water use charges: KSh 5 per cubic metre for domestic, public and livestock use, and KSh 2 per cubic metre for irrigation up to 300 cubic metres a day.

Costs that are not WRA fees

  • NEMA. NEMA approval is mandatory for farms and institutions, and domestic users may get a screening exemption (Nation, April 2026). NEMA approval takes two weeks to three months depending on the area. One driller lists NEMA clearance at KSh 15,000 to 30,000 where it applies (Knight & Hammer, 2025).
  • County. A county “no objection” letter is required in places such as Nairobi, Kiambu and Machakos (Nation). One driller lists county permits at KSh 5,000 to 15,000 (Knight & Hammer, 2025).
  • Total quoted by drillers. Knight & Hammer lists KSh 25,000 to 70,000 for all permits together (2025).

Filing the permit when you build from a distance

Most drillers and hydrogeologists offer to file for you. That is fine, as long as the application is in your name as the landowner or user. Ask for a copy of the application, the file number and the authorisation. If you cannot see the file number, you do not have an authorisation. Drillers describe permit turnaround as the most variable step of a project and give no fixed duration (Boreholes.co.ke, 2026), so plan the build around WRA’s answer and do not mobilise a rig before it arrives.

Before you pay a deposit to a driller, read our checklist in Borehole drilling cost in Kenya. When the borehole is ready, request a solar pump quote. We pass your request to one EPRA-licensed installer and tell you who before sharing your details.

Pumps that fit

Solarpex · AC/DC hybrid 800 W AC/DC, 80 m head
800 WPower80 mMax head5,000Flow L/h
From KSh 46,000 Seen 28 Nov 2026 · skywave.co.ke
Get a confirmed quote
Solarpex · AC/DC hybrid 2 HP AC/DC, 168 m head
1,500 WPower168 mMax head5,000Flow L/h
From KSh 52,000 Seen 28 Nov 2026 · skywave.co.ke
Get a confirmed quote
Solar borehole pumps

Sources

Questions about this

Does a borehole with a solar pump need a hydrogeological survey?
Yes. The Regulations say that where a borehole is to be equipped with a motorised pump, the application must come with a hydrogeological survey report in the prescribed form. A solar pump is a motorised pump. A Category A well with no motorised pumping follows a simpler procedure, and WRA decides the category.
Can I drill first and apply for the permit later?
No. WRA lists drilling without its authorisation as an offence, and NEMA can fine drilling without approval up to KSh 2 million and close the site (Nation, April 2026). A Nakuru school that drilled past 300 m in 2023 without WRA and NEMA approval was fined and its borehole sealed.
How long is the water use permit valid?
Five years. It can be renewed or extended for the same period or a shorter one. Renewal has its own fee, shown in the table above.
How long does WRA take?
The Regulations set some deadlines: 30 days for the local water users' association to comment, 14 days for WRA to decide after the comments, and 31 days to issue the permit once the works pass inspection and your application is complete. We found no published total time from application to permit.
Who must drill the borehole?
A qualified contractor, under the supervision of a qualified and licensed water sector professional, when the borehole is to have a motorised pump. Ask to see the contractor's WRA licence before you pay a deposit.

Get a confirmed quote

Free and without obligation. We pass your request to one EPRA-licensed installer in your county, and tell you who before we share your details.

Common:
We need the county to find a licensed installer near you
What the water is for
Pick all that apply.
Please tick the box so we can pass on your request
No payment now. No spam calls.
What happens next
1We read your request and choose one EPRA-licensed installer who works in your county.
2We tell you who it is. Only then do we share your name, phone and county with them.
3The installer checks your borehole and sends a written, itemised quote. You decide.
Your data Used only to answer this request, under Kenya's Data Protection Act 2019. Never sold, never shared with more than one installer. Privacy policy
Size my pumpGet a quote